Also see the videos "Voices of Tug Hill" (from Lewis County, N.Y., site of the Maple Ridge Wind Farm) and "Life Under a Windplant" (from Meyersdale, Pa.).
wind power, wind energy, wind farms
18.5.3.1. Each wind turbine generator shall be set back from any adjoining lot line a distance equal to 2,600 feet. The Planning Commission may reduce this setback to no less than 2,100 feet. The amount of setback relief approved by the Planning Commission will be based on data provided by the applicant and prepared and certified by a registered Professional Engineer licensed in the State of Michigan, who is practicing in his or her area of competency. Such data shall be subject to review by the County's independent, recognized expert.18.5.4. Maximum Height. Then maximum wind turbine generator or anemometer tower height from the base to the tip of the blade at its highest point shall not exceed 200 feet. The Planning Commission may approve an increased height for a wind turbine generator tower, not to exceed 260 feet from the base to the tip of the blade, if all of the following conditions are met:
18.5.3.2. In addition to the above, a wind turbine generator shall, in all cases, be setback from a public or private road right-of-way or easement a minimum distance equal to six times the height of the wind turbine generator tower as defined in this Ordinance.
18.5.3.3. For any newly proposed wind turbine generator or anemometer tower, a "wind access buffer" equal to a minimum of five (5) rotor diameters shall be observed from any existing off-site wind turbine generator tower.
18.5.19.1. Sensitive environmental areas shall have a setback of between 2 to 5 miles and shall be determined by the Otsego County Planning Commission and the Department of Natural Resources.
18.5.19.2. Scenic areas, including parks, highways, recreational areas, and others as determined by the County and Townships, shall have a setback of not less than 1 mile.
18.5.4.1. The increased height will result in the preservation of a substantial stand of trees, existing land forms or structures that would otherwise be removed to increase wind velocity.wind power, wind energy, wind farms, wind turbines
18.5.4.2. The increased height will not result in increased intensity on lighting of the tower due to FAA requirements.
we will obviously need new energy sources, and the example of the French success with nuclear power (it generates three quarters of their electricity) means it has to be included in the mix of possibilities, as Jim Hansen recently argued in these pages.The French, by the way, are getting desperate about the very dangerous radioactive waste that is piling up at all of their nuclear plants. Maybe McKibben, like Lovelock, will offer to have it buried in his back yard.